  1. The overflow rate for plain sedimentation tanks is about

  2. A.

     500 to 750 liters/hour/ m²

    B.

     1000 to 1250 liters/hour/ m²

    C.

     1250 to 1500 liters/hour/m²

    D.

     1500 to 2000 liters/hour/m²

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided