Home / Civil Engineering / Engineering Economics :: Discussion

Discussion :: Engineering Economics

  1. What is the present worth of two P 100 payments at the end of the third year and fourth year? The annual interest rate is 8%.

  2. A.

     P 150.56

    B.

     P 152.88

    C.

     P 153.89

    D.

     P 151.09

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided