  1. The time which results in the least possible construction cost of an activity, is known as

  2. A.

     Normal time

    B.

     Slow time

    C.

     Crash time

    D.

     Standard time

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided