Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same
A.
A is correct but R is not correct |
B.
R is correct but A is not correct |
C.
Both A and R is correct |
D.
Both A and R is incorrect |
Answer : Option A
Explanation :
Explanation Not Provided