  1. Whenever an activity has zero total float, then

  2. A.

     Free float of the activity must be zero but independent float need not be zero

    B.

     Independent float must be zero but free float need not be zero

    C.

     Free float and independent float both must be zero

    D.

     Free float and independent float both need not be zero

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided