  1. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

  2. A.

     Duration

    B.

     Total float

    C.

     Free float

    D.

     Interfering float

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided