  1. Economic saving of time results by crashing

  2. A.

     Cheapest critical activity

    B.

     Cheapest noncritical activity

    C.

     Costliest critical activity

    D.

     Costliest noncritical activity

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided