  1. Consider the following activities in a building construction:
    1. Concreting of roof slabs
    2. Brick-jelly lime concrete terracing
    3. Erection of form work for slab
    4. Construction of parapet wall in terrace
    The correct sequence of these activities is

  2. A.

     1, 3, 2, 4

    B.

     3, 1, 4, 2

    C.

     3, 1, 2, 4

    D.

     1, 3, 4, 2

    View Answer

    Workspace

    Answer : Option C

    Explanation :