- Select the incorrect statement.
A.
A critical path always begins at the very first event. |
B.
A critical path always terminates at the last event. |
C.
Critical activities control the project duration. |
D.
Critical activity is the one for which free float is zero. |
Answer : Option D
Explanation :
Explanation Not Provided