Discussion :: Construction Planning and Mgmt
- Select the incorrect statement.
A.
Start float and finish float are always equal |
B.
Total float can be either start float or finish float |
C.
Start float and finish float need not be equal |
D.
Start float and finish float are the differences between activity times and not event times |
Answer : Option C
Explanation :
Explanation Not Provided
Be The First To Comment