Discussion :: Construction Planning and Mgmt
- Select the incorrect statement.
A.
Earliest start of an activity is the early event time of the node it leaves |
B.
Latest finish of an activity is the late event time of the node it enters |
C.
Latest start of an activity is its latest finish minus its duration |
D.
None of the above |
Answer : Option D
Explanation :
Explanation Not Provided
Be The First To Comment