- Pick up the correct statement from the following:
A.
The float may be positive, zero or negative |
B.
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed |
C.
If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
D.
All the above |
Answer : Option D
Explanation :
Explanation Not Provided