Discussion :: Construction Planning and Mgmt
- Pick up the correct statement from the following:
|
A.
The float may be positive, zero or negative |
|
B.
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed |
|
C.
If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
|
D.
All the above |
Answer : Option D
Explanation :
Explanation Not Provided
Be The First To Comment

Whatsapp
Facebook