Home / Civil Engineering / Construction Planning and Mgmt :: Discussion

Discussion :: Construction Planning and Mgmt

  1. Pick up the correct statement from the following:

  2. A.

     The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

    B.

     The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

    C.

     The difference between total float and free float, is called interfering float

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided