  1. Pick up the correct statement from the following:

  2. A.

     The difference of latest occurrence time and earliest expected time, is called slack

    B.

     The activities connecting the events having zero slack, lie on the critical path

    C.

     The critical path consumes the maximum time

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided