- Pick up the correct statement from the following:
A.
The difference of latest occurrence time and earliest expected time, is called slack |
B.
The activities connecting the events having zero slack, lie on the critical path |
C.
The critical path consumes the maximum time |
D.
All the above |
Answer : Option D