  1. Pick up the incorrect statement from the following:

  2. A.

     The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity

    B.

     The difference between the maximum time available for the job and actual time it consumes, is called total float

    C.

     The difference between the latest start time and earliest start time of an activity, is called total float

    D.

     None of these

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided