- Pick up the incorrect statement from the following:
A.
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity |
B.
The difference between the maximum time available for the job and actual time it consumes, is called total float |
C.
The difference between the latest start time and earliest start time of an activity, is called total float |
D.
None of these |
Answer : Option D
Explanation :
Explanation Not Provided