Discussion :: Construction Planning and Mgmt
- Pick up the correct statement from the following:
A.
Programme Evaluation and Review Technique, is event oriented |
B.
Programme Evaluation and Review Technique is not event oriented |
C.
Critical Path Method is event oriented |
D.
Critical Path Method is not event oriented |
Answer : Option A
Explanation :
Explanation Not Provided
Be The First To Comment