  1. Pick up the correct statement from the following:

  2. A.

     Forward pass is used for calculating earliest expected time

    B.

     Backward pass is used for calculating the latest occurrence time

    C.

     Maximum value of earliest expected time is used if there is more than one value of any event

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided