  1. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

  2. A.

     Total float

    B.

     Free float

    C.

     Interfering float

    D.

     Independent float

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided