Discussion :: Construction Planning and Mgmt
- Free float is mainly used to
|
A.
Identify the activities which can be delayed without affecting the total float of preceding activity |
|
B.
Identify the activities, which can be delayed without affecting the total float of succeeding activity |
|
C.
Establish priorities |
|
D.
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities |
Answer : Option B
Explanation :
Explanation Not Provided
Be The First To Comment

Whatsapp
Facebook