- Free float for any activity is defined as the difference between
|
A.
its earliest finish time and earliest start time for its successor activity |
|
B.
its latest start time and earliest start time |
|
C.
its latest finish time and earliest start time for its successor activity |
|
D.
its earliest finish time and latest start time for its successor activity |
Answer : Option A
Explanation :
Explanation Not Provided