  1. Total float for any activity is defined as the difference between

  2. A.

     Its latest finish time and earliest start time for its successor activity

    B.

     Its latest start time and earliest start time

    C.

     Its latest start time and earliest finish time

    D.

     Its earliest finish time and earliest start time for its successor activity

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided