Discussion :: Construction Planning and Mgmt
- Total float for any activity is defined as the difference between
A.
Its latest finish time and earliest start time for its successor activity |
B.
Its latest start time and earliest start time |
C.
Its latest start time and earliest finish time |
D.
Its earliest finish time and earliest start time for its successor activity |
Answer : Option B
Explanation :
Explanation Not Provided