  1. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

  2. A.

     3.5 and 5/6

    B.

     5 and 25/36

    C.

     3.5 and 25/36

    D.

     4 and 5/6

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided