  1. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

  2. A.

     to + 3tm+ tp/3

    B.

     to + 4tm+ tp/4

    C.

     to + 4tm+ tp/5

    D.

     to + 4tm+ tp/6

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided