  1. Pick up the correct statement from the following:

  2. A.

    Forward pass is used for calculating earliest expected time

    B.

    Backward pass is used for calculating the latest occurence time

    C.

    Maximum value of earliest expected time is used if there are more than one value of any event

    D.

    Minimum value of latest occurrence time is used if there are more than one value of any event

    E.

    All the above.

    View Answer

    Workspace

    Answer : Option E

    Explanation :

    No answer description available for this question.