Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
|
A.
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity |
|
B.
Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity |
|
C.
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time |
|
D.
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time |
|
E.
All the above. |
Answer : Option E
Explanation :
No answer description available for this question.