  1. In CPM analysis,

  2. A.

    emphasis is given to activities

    B.

    uncertainties are not allowed

    C.

    activities are represented by arrows

    D.

    beginning and end of an activity, are denoted by nodes

    E.

    all the above.

    View Answer

    Workspace

    Answer : Option E

    Explanation :

    No answer description available for this question.