  1.  

    For completion of a project, the critical path of the network represents

  2. A.

    minimum time

    B.

    maximum time

    C.

    maximum cost

    D.

    minimum cost.

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question.