Home / Civil Engineering / Construction Management :: Discussion

Discussion :: Construction Management

  1. Critical path lies along the activities having total float

  2. A.

    positive

    B.
    negative
    C.
    zero
    D.

    same.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.