  1. CPM is

  2. A.

    synthesising in concepts

    B.

    is built of activities oriented programme

    C.

    is based on time estimate

    D.

    is used for repetitive works

    E.

    all the above.

    View Answer

    Workspace

    Answer : Option E

    Explanation :

    No answer description available for this question.