  1. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

  2. A.

    duration

    B.

    total flat

    C.

    free float

    D.

    interfering float.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.