  1. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

  2. A.

    \( \frac { a+m+b } { 6} \)

    B.

    \( \frac { a+2m+b } { 6} \)

    C.

    \( \frac { a+4m+b } { 6} \)

    D.

    \( \frac { a+5m+b } { 6} \)

    Answer : Option C

    Explanation :

    No answer description available for this question.