If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
A.
\( \frac { a+m+b } { 6} \) |
B.
\( \frac { a+2m+b } { 6} \) |
C.
\( \frac { a+4m+b } { 6} \) |
D.
\( \frac { a+5m+b } { 6} \) |
Answer : Option C
Explanation :
No answer description available for this question.