  1. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

  2. A.

    EF = ES + D

    B.

    LS = LF - D

    C.

    LF = LS + D

    D.
    D = EF - ES
    E.

    all the above.

    View Answer

    Workspace

    Answer : Option E

    Explanation :