  1. For providing a raft foundation, the following activities are involved

    1. ramming the foundation bed
    2. excavation of the soil upto required depth
    3. laying the reinforcement over the foundation bed
    4. curing the cement concrete placed over reinforcement
    5. pouring the cement concrete over the reinforcement.
  2. A.

    1, 2, 3, 4, 5

    B.

    5, 4, 3, 2, 1

    C.

    2, 1, 3, 5, 4

    D.
    3, 2, 5, 1, 4.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.