  1. It takes 6 hours to dry a wet solid from 50% moisture content to the critical moisture content of 15%. How much longer it will take to dry the solid to 10% moisture content, under the same drying conditions? (The equilibrium moisture content of the solid is 5%).

  2. A.
    15 min
    B.
    51 min
    C.
    71 min
    D.
    94 min

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.