Discussion :: Chemical Engineering Plant Economics

  1. If 'S' is the amount available after 'n' interest periods for an initial principal 'P' with the discrete compound interest rate 'i', the present worth is given by

  2. A.

     (1 + i)n/S

    B.

     S/(1 + i)n

    C.

     S/(1 + in)

    D.

     S/(1 + n)i

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided