  1. On-off control

  2. A.
    fully opens the final control element, when the measured variable is below the set point.
    B.
    fully closes the final control element, when the measured variable is above the set point.
    C.
    is a two position control (fully open or fully closed) control adequate to control a process with slow reaction and minimum dead time or transfer lag.
    D.
    none of these.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.