  1. A, B, and C can finish a work in 18, 27, and 36 days respectively. All three start working together. A leaves the job after 8 days, and B leaves the job 6 days before it is finished, then the work will be finished in how many days?
  2. A.
    12 days
    B.
    13 days
    C.
    18 days
    D.
    36 days

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Note: Assume the total work = LCM of the given days

    Take the LCM of days = LCM of (18, 27, and 36) = 108
    Let the total work = 108

    A's one day work = 108/18 = 6 units
    B's one day work = 108/27= 4 units
    C's one day work = 108/36= 3 units

    ATQ, A works only for 8 days.
    So, A's total work done = 8 * 6 = 48
    So, remaining work = 108-48 = 60 work done by (B and C).

    If (B+C) work till last, they can finish the work in 60/7= 8.57 days.

    But ATQ, B left the job 6 days before it is completed.
    Assume that B is not left the work than B's 6-day work is also included in the total work.
    So, B's 6 day work = 6 * 4 = 24 units

    Now, the total remaining work = 60+24 = 84units.

    (B+C)'s one day efficiency = 7

    So, to complete the work it requires = 84/7 = 12 days.