  1. A and B individually can finish a job in 20 and 30 days respectively. They start working together, and B leaves the job 5 days before completion, now the work will be finished in how many days?
  2. A.
    12 days
    B.
    14 days
    C.
    16 days
    D.
    18 days

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Note: Assume the total work = LCM of the given days

    Take the LCM of days = LCM of (20 and 30) = 60
    Let the total work = 60

    A's one day work = 60/20 = 3 unit
    B's one day work = 60/30= 2 unit

    If (A+B) work, then they can finish the work in 60/5 = 12 days.

    But ATQ, B left the job 5 days before
    Assume that B has not left the work than B's 5-day work also included in the total work.
    i.e., B's 5 day work = 5 * 2 = 10 units

    Now, the total work = 60+10 = 70units
    If (A+B)'s one day efficiency = 5

    So, to complete the work it requires = 70/5 = 14 days.