- A contractor undertakes to complete a work in 120 days with the help of 100 workers. After 45 days, he finds that only ¼ of the work has been completed. To complete the remaining work, how many extra workers will be required?
Answer : Option A
Explanation :
Apply formula: [Man1 * day1* hour1*]/ work1 = [Man2 * day2* hour2*]/ work2
ATQ, target = 120 days
M1 = 100, M2 =?
D1 = 45, D2 = 120-45 = 75
Let total work = 1
W1 = ¼, W2= 1-1/4 = ¾
Assume H1 = H2 = 1
Now, apply the formula
[M1 * D1 * H1]/ W1 = [M2 * D2 * H2]/ W2
Now, [H1 = H2 = 1]
So, [M1 * D1 * W2] = [M2 * D2 * W1]
Or, (100 * 45 * 3/4) = (M2 * 75 * ¼)
Or, M2 = 180