  1. A contractor undertakes to complete a work in 120 days with the help of 100 workers. After 45 days, he finds that only ¼ of the work has been completed. To complete the remaining work, how many extra workers will be required?
  2. A.
    80 workers
    B.
    180 workers
    C.
    160 workers
    D.
    100 workers

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Apply formula: [Man1 * day1* hour1*]/ work1 = [Man2 * day2* hour2*]/ work2

    ATQ, target = 120 days

    M1 = 100, M2 =?
    D1 = 45, D2 = 120-45 = 75
    Let total work = 1
    W1 = ¼, W2= 1-1/4 = ¾
    Assume H1 = H2 = 1

    Now, apply the formula

    [M1 * D1 * H1]/ W1 = [M2 * D2 * H2]/ W2
    Now, [H1 = H2 = 1]
    So, [M1 * D1 * W2] = [M2 * D2 * W1]

    Or, (100 * 45 * 3/4) = (M2 * 75 * ¼)
    Or, M2 = 180

    So, M2 - M1 = 180 -100 = 80 extra workers will be required.