A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
Answer : Option C
Explanation :
A's 1 hour's work = | 1 | ; |
4 |
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | 1 | + | 1 | = | 7 | . | ||
4 | 3 | 12 |
B's 1 hour's work = | 7 | - | 1 | = | 1 | . | ||
12 | 2 | 12 |
B alone will take 12 hours to do the work.