Discussion :: Time and Work
-
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
Answer : Option D
Explanation :
(P + Q + R)'s 1 hour's work = | 1 | + | 1 | + | 1 | = | 37 | . | ||
8 | 10 | 12 | 120 |
Work done by P, Q and R in 2 hours = | 37 | x 2 | = | 37 | . | ||
120 | 60 |
Remaining work = | 1 - | 37 | = | 23 | . | ||
60 | 60 |
(Q + R)'s 1 hour's work = | 1 | + | 1 | = | 11 | . | ||
10 | 12 | 60 |
Now, | 11 | work is done by Q and R in 1 hour. |
60 |
So, | 23 | work will be done by Q and R in | 60 | x | 23 | = | 23 | hours 2 hours. | ||
60 | 11 | 60 | 11 |
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
Be The First To Comment