A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
Answer : Option C
Explanation :
| B's 10 day's work = | ![]() | 1 | x 10 | ![]() | = | 2 | . |
| 15 | 3 |
| Remaining work = | ![]() | 1 - | 2 | ![]() | = | 1 | . |
| 3 | 3 |
| Now, | 1 | work is done by A in 1 day. |
| 18 |
![]() | 1 | work is done by A in | ![]() | 18 x | 1 | ![]() | = 6 days. |
| 3 | 3 |