P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
Answer : Option A
Explanation :
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P's1 hour's work = | 1 | and Q's 1 hour's work = | 1 | . |
| 96 | 80 |
| (P + Q)'s 1 hour's work = | ![]() | 1 | + | 1 | ![]() | = | 11 | . |
| 96 | 80 | 480 |
| So, both P and Q will finish the work in | ![]() | 480 | ![]() | hrs. |
| 11 |
Number of days of 8 hours each = | ![]() | 480 | x | 1 | ![]() | = | 60 | days = 5 | 5 | days. |
| 11 | 8 | 11 | 11 |