Discussion :: Time and Work
-
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Answer : Option B
Explanation :
Work done by X in 4 days = | 1 | x 4 | = | 1 | . | ||
20 | 5 |
Remaining work = | 1 - | 1 | = | 4 | . | ||
5 | 5 |
(X + Y)'s 1 day's work = | 1 | + | 1 | = | 8 | = | 2 | . | ||
20 | 12 | 60 | 15 |
Now, | 2 | work is done by X and Y in 1 day. |
15 |
So, | 4 | work will be done by X and Y in | 15 | x | 4 | = 6 days. | ||
5 | 2 | 5 |
Hence, total time taken = (6 + 4) days = 10 days.
Be The First To Comment