A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
Answer : Option C
Explanation :
| (A + B + C)'s 1 day's work = | 1 | ; |
| 6 |
| (A + B)'s 1 day's work = | 1 | ; |
| 8 |
| (B + C)'s 1 day's work = | 1 | . |
| 12 |
(A + C)'s 1 day's work |
| ||||||||||||||
| |||||||||||||||
| |||||||||||||||
|