Home / Arithmetic Aptitude / Time and Work :: Discussion

Discussion :: Time and Work

  1. A can do a certain job in 12 days. B is 60% more efficient than A. Then Number of days it takes B to do the same piece of work is?
  2. A.
    6
    B.
    6 ¼
    C.
    7 ½
    D.
    8

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Ratio of times taken by A and B = 160 : 100 = 8 : 5 



Be The First To Comment