- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Answer : Option B
Explanation :
Work done by X in 4 days = (1/20 * 4) = 1/5
Remaining work = (1 - 1/5) = 4/5