  1. Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is?
  2. A.
    15
    B.
    16
    C.
    18
    D.
    25

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Ratio of times taken by Sakshi and Tanys = 125:100 = 5:4

    Suppose Tanya takes x days to do the work.