  1. A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6AM and they work alternately for one hour each. When will the work be completed?
  2. A.
    4 days
    B.
    7 days
    C.
    5 days
    D.
    6 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Work done by A and B in the first two hours, working alternately = First hour A + Second hour B = 1/4 + 1/12 = 1/3.
    Total time required to complete the work = 2 * 3 = 6 days.