Discussion :: Time and Work
- 30 men can do a work in 40 days. When should 20 men leave the work so that the entire work is completed in 40 days after they leave the work?
Answer : Option B
Explanation :
Total work to be done = 30 * 40 = 1200
Let 20 men leave the work after 'P' days, so that the remaining work is completed in 40 days after they leave the work.
40P + (20 * 40) = 1200
40P = 400 => P = 10 days